6/29/23 Three Week Look Ahead

 CONCRETE

PHASE 1 | BLDG C CONCRETE Fri 2/3/23 Wed 8/16/23

    Bldg C | Concrete Ramps & Stairs Wed 7/5/23 Wed 8/16/23

    Central Ave | Concrete Ramps & Stairs Wed 7/5/23 Wed 8/16/23

    Willow St | Concrete Ramps & Stairs Wed 7/5/23 Wed 8/16/23

     Bldg C | Slab on Grade Fri 6/9/23 Wed 7/12/23

PHASE 2 | BLDG B CONCRETE Tue 3/28/23 Fri 2/9/24

    Bldg B | Foundations Tue 3/28/23 Thu 6/29/23

PHASE 3 | BLDG A CONCRETE Thu 5/25/23 Thu 6/27/24

    Bldg A | Foundations Thu 5/25/23 Tue 9/19/2


STRUCTURAL STEEL

PHASE 2 | BLDG B STRUCTURAL STEEL Wed 6/28/23 Thu 8/3/23


*Please note Central Avenue and Watts Street will be paved July 17. More information on this will be forthcoming from the City. 