1/31/24 Important Updates

All, please see below two important dates coming up:

  • National Grid will be digging test pits at the intersection of Watts and Highland Street February 1st and 2nd. Both streets will be kept open to traffic while the work is being conducted
  • Watts street will be closed on February 20th from 7:00 AM - 2:00 PM due to a concrete pour. This is the first of three pours that will be conducted in February and March. This blog will be updated prior to each pour.