2/2/2024 Updates

    Construction continues to move forward at the Chelsea Innes project. See below for an abbreviated, high level schedule:


  • BLDG B Siding (Watts street side, as seen below): Scheduled to finish 2/8/2024
  • BLDG B Drywall continues to progress, with floors 4, 5, and 6 having drywall in Block A
  • BLDG A Sixth floor framing is complete on the East elevation (as seen below)

Please note, the jobsite will be open tomorrow, 2/3/2024

See image below:

Building B siding on the left; Building A roof trusses going up straight ahead.